Eaton BladeUPS User Manual page 76

For use with eaton bladeups 5 kva to 60 kva (n+1) systems
Hide thumbs Also See for BladeUPS:
Table of Contents

Advertisement

3.
Slide the battery trays into the cabinet (see Figure 56 for two battery string installations and Figure 57 for
single-string installations). Verify that each tray is properly aligned before sliding the tray in.
NOTE
When installing single-string battery trays for BladeUPS 5.1 kVA, always install the
single-string trays in the bottom battery compartment.
4.
When a tray is fully installed, tuck the plastic handle on the end of the tray into place.
Figure 56. Installing the UPS Battery Trays (Two Battery Strings)
Figure 57. Installing the UPS Single-string Battery Trays for 5.1 kVA BladeUPS
5.
Reinstall the battery cover plate.
Eaton BladeUPS 5.1 kVA to 60 kVA (N+1) User's Guide 164201649—Rev 9 www.eaton.com/powerquality
Standard System Installation
70

Advertisement

Table of Contents
loading