Caution – Before proceeding with these instructions, turn off the power from the DC
power source through the circuit breakers.
2. Route the power cables in the rack and secure the cables with nylon tie wraps.
3. Connect the chassis ground wire to the facility ground and ensure that this
connection has proper bonding.
4. Connect the -48V or -60V Return to the -48V or -60V wires to the circuit breaker.
5. Connect the power wiring to the server by plugging each power cable into the
server power supply units.
6. When you are ready to power up the server, close the circuit breaker and follow
the booting procedure.
See
"Powering On the Server for the First Time" on page
Related Information
"Powering On the Server for the First Time" on page 77
■
77.
Assembling and Connecting DC Power Cords