UPS System Installation
Figure 31. ISBM Section Conduit and Wire Entry Locations
Top Entry Conduit Landing for AC
Input and Output, and DC Input
(Remove panel to drill or punch
conduit holes.)
TOP VIEW
BOTTOM VIEW
Bottom Entry Conduit Landing for AC
Input and Output, and DC Input
(Remove panel to drill or punch
conduit holes.)
4.
Locate the external wiring terminal hardware kit packed on the bottom left side of the ISBM section.
5.
Using hardware from the external wiring terminal hardware kit (see
rectifier input power wiring from the utility source to the rectifier input terminals in the ISBM section. See
paragraph
6.
If installing a UPS configured as an Input Output Module (IOM), proceed to Step 8; otherwise, proceed to
Step 7.
7.
Using hardware from the external wiring terminal hardware kit (see
and Neutral (if required) bypass input power wiring from the utility source to the bypass input terminals and
66
Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201764—Rev 14
3.2.4 UPS System Power Wiring Preparation
Front
Interface Entry Conduit Landings for TB1
through TB3 Wiring and X-Slot Connections
(Remove panels to drill or punch conduit holes.)
Front
Table
14), connect phase A, B, and C
for wiring and termination requirements.
Table
14), connect phase A, B, and C,