Figure 17. Removing the ISBM Section Right Side Shipping Bracket
ISBM Removable
Front Panels
Pallet
4.
Using a forklift (see the caution statement at the beginning of this procedure), raise the UPS cabinet
section until the cabinet bottom clears the pallet by approximately 3 mm (1/8").
5.
Pull the pallet from under the UPS cabinet. Discard or recycle the pallet in a responsible manner.
6.
Carefully lower the UPS cabinet until the cabinet base contacts the floor.
7.
Repeat Steps 2 through 6 for the remaining cabinet.
8.
Proceed to paragraph
Right Side Shipping
Bracket
4.3 Mechanically Joining the
Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201764—Rev 14
Sections.
UPS System Installation
Shipping Bracket
Bolts
Shipping Bracket
Bolts
49