Eaton Power Xpert 9395 Installation And Operation Manual page 109

Ups 1000-1100 kva, for use with three upm 650-825 kva and four upm 1000-1100 kva ups
Hide thumbs Also See for Power Xpert 9395:
Table of Contents

Advertisement

UPS System Installation
Distributed Bypass Installation Checklist
o Each cabinet in the distributed bypass system is placed in its installed location.
o All conduits and cables are properly routed to the UPS cabinets and to the tie cabinet or distribution panel.
o All power cables are properly sized and terminated.
o A ground conductor is properly installed.
o Controller Area Network (CAN) wiring between the UPS cabinets is properly installed.
o Pull-chain wiring between the UPS cabinets is properly installed.
o Adequate workspace exists around the UPS cabinets, the tie cabinet, and other cabinets.
o Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.
88
Eaton Power Xpert 9395 UPS Installation and Operation Manual 164201764—Rev 14

Advertisement

Table of Contents
loading

This manual is also suitable for:

Power xpert 9395p

Table of Contents