Site Preparation Checklist For Ex4100 And Ex4100-F Switches - Juniper EX4100 Hardware Manual

Hide thumbs Also See for EX4100:
Table of Contents

Advertisement

Site Preparation Checklist for EX4100 and EX4100-
F Switches
The checklist in
Table 27 on page 85
for EX4100 and EX4100-F switch installation.
Table 27: Site Preparation Checklist
Item or Task
Environment
Verify that environmental factors
such as temperature and humidity
are within switch tolerances.
Power
Measure the distance between
external power sources and the
switch installation site.
Locate sites to connect system
grounding.
Calculate the power consumption
requirements.
Hardware Configuration
Choose the number and types of
switches you want to install.
summarizes the tasks you need to perform when preparing a site
For More Information
"Environmental Requirements and
Specifications for EX4100 and
EX4100-F Switches" on page 88
"Clearance Requirements for
Airflow and Hardware Maintenance
for EX4100 and EX4100-F
Switches" on page 93
"AC Power Supply in EX4100
and EX4100-F Switches" on
page 68
"DC Power Supply in EX4100
Switches" on page 78
"EX4100 and EX4100-F Switches
Hardware Overview" on page 2
Performed By
Date
85