Figure 3-18 Fit the metal shell onto the twisted-pair cable
Step 4 Fit the metal shell onto the twisted-pair cable until the shield layer is covered completely. Along
the edge of the metal shell, cut off the aluminum foil shield layer and ensure that there is no
surplus copper wire. The exposed twisted-pair cable is about 20 mm (0.79 in.) long, as shown
in
Figure
Figure 3-19 Removing the shield layer of a twisted-pair cable (unit: mm (in.))
Step 5 Based on the colors, lead the four pairs of twisted-pair wires through the wire holder, as shown
in
Figure 3-20
Figure 3-20 Leading wires through the wire holder
Issue 02 (2011-09-10)
3-19.
and
Figure
3-21.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 On-site Cable Assembly and Installation
32

Advertisement

loading

This manual is also suitable for:

Ne80e