3.2 Assembling Power Cables
This section describes how to assemble power cables with OT terminals, JG terminals, and cord
end terminals.
3.2.1 Assembling the OT Terminal and Power Cable
This section describes how to assemble an OT terminal and a power cable.
Context
Figure 3-1
Figure 3-1 Components of an OT terminal and a power cable
A Heat-shrinkable tubing
Procedure
Step 1 Based on the cross-sectional area of the cable conductor, strip a part of the insulation. This
exposes length L1 of the conductor, as shown in
are listed in
Issue 02 (2011-09-10)
– Keep all the conductors clean and aligned.
NOTE
The connectors, cables, and tools provided by different vendors may be different. The figures in this
document are only for your reference.
shows the components of an OT terminal and a power cable.
Table
3-1.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
3 On-site Cable Assembly and Installation
B. Bare crimping terminal
Figure
C. Insulation
D. Conductor
3-2. The recommended values of L1
21