Procedure
To partly or completely deactivate the installation of the setup files by means of the PCU
Installer, proceed as follows:
1. Open the PCUInst.ini configuration file in the C:\ProgramData\Siemens
\MotionControl\user\System\etc\PCUInst.ini directory.
2. Deactivate the start of the PCU Installer in the desired phase:
– To deactivate the PCU Installer during system operation, change the relevant key value
– To only deactivate the PCU Installer while a specific application is being executed (e.g.
– To deactivate the PCU Installer during run-up, change the relevant key value in
3. Save and close the file.
Further information
● For information on all configuration options, see Reference to the PCUInst.ini configuration
file (Page 236).
● Windows support: Start Windows 10 in the safe mode
help/12376/windows-10-start-your-pc-in-safe-mode)
10.4.5.4

Copying and adapting the configuration file

You can define PCU Installer operation in the associated configuration file. To do this, you must
first copy the configuration file to a user directory.
Alternatively, you can copy a template in which the PCU Installer has already been activated
(Page 233).
For example, you can configure the following in the configuration file:
● Which directories have been checked how many times for new setup packages.
● That installations are not started automatically while certain software is active.
A list of all setting options can be found under Reference to the PCUInst.ini configuration file
(Page 236).
Precondition
● The Service Desktop is active
● The PCU Installer has not been configured yet and there is no adapted PCUInst.ini
configuration file
MCU commissioning: NC, PLC, Drive
Commissioning Manual, 02/2020, A5E47437618B AB
10.4 Installing and configuring updates and automation software
in the [processing_systemphase] section: StartState=stopped.
SINUMERIK Commissioning), enter the file name of the relevant application in
the [noactivation] section, e.g. APP001=run_hmi.exe
(You can specify any number of applications,
e.g. APP002=Siemens.Automation.Portal.exe)
the [processing_loginphase] section: StartState=stopped.
Installing and setting up PCU Base for IPC
(https://support.microsoft.com/en-us/