To configure the Cascade Controller to the actual system and the desired control strategy, it is recommended to follow the below sequence, starting with
parameter group 25-0*
System Settings
Bandwidth Settings
Parameters in 25-2*
done at the commissioning of the plant.
NB!
The Cascade Controller is supposed to operate in closed loop controlled by the built-in PI controller (Closed Loop selected in
ration Mode
destaged, but the variable speed pump will still be controlled by the frequency converter, now as an open loop configuration:
240
and next parameter group 25-5*
Staging settings
and 25-4*
, par. 1-00
Configuration Mode
). If
Open Loop
MG.11.C9.02 - VLT
in the Design Guide.
Alternation Settings
. These parameter can normally be set in advance.
, will often be dependent on the dynamic of the system and final adjustment to be