The installation sequence is as follows:
1. Verify that the required environmental conditions and utilities exist.
2. Unpack and inspect the melter.
3. Mount the transformer/melter onto the parent machine or support
structure.
4. Configure the electrical service.
5. Connect a compressed air supply.
6. Connect hot melt hoses and guns.
7. Set up the melter to work with the manufacturing process.
8. (Optional) Install inputs and outputs.
9. Install optional equipment.
10. Connect a gun driver, pattern controller, or timer.
11. Flush the melter.
12. (Optional) Set up communications between the melter and a PC.
The instructions provided in this section are intended to be used by
personnel who have experience in the following subjects:
S
Hot melt application processes
S
Industrial power and control wiring
S
Industrial mechanical installation practices
S
Basic process control and instrumentation
3-3