Site preparation

For information on general computer room site preparation, see the HPE Generalized Site Preparation
Guide on the Hewlett Packard Enterprise website:
http://www.hpe.com/info/Integrity_Servers-docs
IMPORTANT:
To avoid hardware damage, allow the thermal mass of the product to equalize to the temperature
and humidity of the installation facility after removing the shipping materials. A minimum of one hour
per 10° C (50° F) of temperature difference between the shipping facility and installation facility is
required.
Server dimensions and weight
Table 2: Rack or pedestal-mounted server dimensions
Dimensions and weight
Data center server dimensions
Depth
Width
Height
Weight
Rack unit
Grounding
The site building must provide a safety ground/protective earth for each AC service entrance to all
cabinets.
Install a PE conductor that is identical in size, insulation material, and thickness to the branch-circuit
supply conductors. The PE conductor must be green with yellow stripes. The earthing conductor is to be
connected from the unit to the building installation earth or, if supplied by a separately derived system, at
the supply transformer or motor-generator set grounding point.
Server electrical specifications
System power specifications
Available power (output) is the maximum DC power that the power supply can supply to the system.
Maximum input power is what the power supply requires from the AC line to deliver that maximum DC
output (given worst case efficiency and maximum loading).
Maximum input current is the worst case/highest current given the lowest input voltage and the maximum
input power.
20
Site preparation
Value
69.2 cm (27.25 in)
48.3 cm (19 in)
8.9 cm (3.5 in)
Maximum configuration – 30 kg (66 lb)
2U