Installation Sequence And Checklist - HPE Integrity rx2800 i2 series User's & Service Manual

Table of Contents

Advertisement

Avoid touching pins, leads, or circuitry.
Always be properly grounded when touching a static-sensitive component or assembly.

Installation sequence and checklist

Step
Description
1
Perform site preparation (see Site preparation on page 20).
2
Install the server into a rack or pedestal.
3
Connect cables to the server.
a. Connect the AC input power cable.
b. Connect LAN core I/O cable.
c. Connect the iLO 3 MP LAN cable.
4
Connect and set up the console for access.
5
Power on the server.
6
From iLO MP, access UEFI.
7
Boot the operating system.
8
Using Smart Update Manager, download the latest firmware.
Installing the server into a rack or pedestal
Rack installation
Hewlett Packard Enterprise rack
Hewlett Packard Enterprise servers that are installed into racks are shipped with equipment-mounting
slides. The HPE 2U Quick Deploy Rail System Installation Instructions for HPE Products ships with each
set of slides. Follow the steps in this installation guide to determine where and how to install the server
into the rack.
For more information on rack deployment, stabilization and transportation, see the 10000 Series G2 Rack
Best Practices Guide.
http://www.hpe.com/info/rackandpower
Non-Hewlett Packard Enterprise rack
For information on installing a HPE Integrity rx2800 i2 server in a third party rack, see the QuickSpecs
located on the rx2800 i2 server product page.
http://www.hpe.com
26
Installation sequence and checklist
Completed