Preparing for System Installation

7.3
7.3.1
7.3.2
3
Installation Requirement
Floor Plans
System Design
Power available:
Fusion Main Hub (AC)
Fusion Expansion Hub (AC)
To RAU (DC)
Fusion Main Hub (DC)
Fusion Expansion Hub (DC)
Rack space available
(Main and Expansion Hub)
Wallmount Fusion Main Hub
Clearance for air circulation:
Fusion Main or Expansion Hub
RAU
Suitable operating environment:
Fusion Main or Expansion Hub
RAUs
Donor Antenna-to-Fusion Configuration (for each Fusion Band)
Donor Antenna
Lightning Arrestor or
Surge Suppressor
7-6
CONFIDENTIAL
Preparing for System Installation

Pre-Installation Inspection

Follow this procedure before installing Fusion equipment:
Verify the number of packages received against the packing list.
1.
Check all packages for external damage; report any external damage to the ship-
2.
ping carrier. If there is damage, a shipping agent should be present before you
unpack and inspect the contents because damage caused during transit is the
responsibility of the shipping agent.
Open and check each package against the packing list. If any items are missing,
3.
contact ADC customer service (refer to Section 7.2.2 on page 7-4).
If damage is discovered at the time of installation, contact the shipping agent.
4.

Installation Checklist

Installation Checklist
Table 7-2
Consideration
Installation location of equipment clearly marked
Used to verify frequency bands after installation
Hub's power cord is 2 m (6.5 ft) long.
115/230V, 2/1A, 50–60 Hz
115/230V, 6/3A, 50-60 Hz
54V (from the Hub)
38–64VDC, 2.5A
38–64VDC, 14A
89 mm (3.5 in.) high (2U)
Hub must be mounted on 3/4" plywood backboard.
76 mm (3 in.) front and rear, 51 mm (2 in.) sides
76 mm (3 in.) all around
Indoor location only
0° to +45°C (+32° to +113°F)
5% to 95% non-condensing humidity
–25° to +45°C (–13° to +113°F)
5% to 95% non-condensing humidity
Installed, inspected; N-male to N-male coaxial cable to lightning arrestor/surge
suppressor
Installed between roof-top antenna and repeater; N-male to N-male 50 Ohm coax-
ial cable and outdoor cables longer than 140 feet.