3.
Tighten the retaining screw to secure the front I/O assembly to the motherboard.
4.
Connect the cable.
5.
Install the main module back into the server.
See
"Install the Main Module" on page
Related Information
"Remove the Front I/O Assembly" on page 127
■
"Verify the Front I/O Assembly" on page 131
■
Verify the Front I/O Assembly
1.
Ensure that you have completed the following:
Applied power to the server.
■
See
"Connect the Power Cords" on page
■
Started the system.
See
"Power On the Server (Oracle ILOM)" on page
Log in to Oracle ILOM.
2.
See
"Log In to Oracle ILOM (Service)" on page
3.
Start the faultmgmt shell.
start SP/faultmgmt/shell
->
Are you sure you want to start the faultmgmt shell (y/n)?
95.
191.
192.
28.
y