HN9200 Satellite Modem Installation Guide
42
1038622-0001 Revision B
Note: The Perform ACP checkbox is automatically checked if ACP is enabled at the
NOC. If it is not automatically checked, likely reasons are that the NOC does not support
ACP, ACP is not enabled at the NOC, or there is a problem with the ACP server.
Note: The ACP test is required for Ku-band customers in the United States and Canada;
for customers outside the United States and Canada, it is optional.
2. Click Next.
3. On the Transmit Antenna Pointing screen, click Manual to initiate the manual
cross-polarization test.

Figure 32: Initiating a manual cross-polarization test

Be ready to adjust the antenna. For antenna adjustment instructions, see the antenna installation
guide.
Note: The manual cross-polarization test times out 3 to 5 minutes after you click the
Manual button. Therefore you must complete any antenna adjustments required to
achieve maximum transmit isolation within this time.
4. In the Warning dialog that warns that the transmitter is actively powered on during the manual
cross-polarization test, click Continue.