Preparing for installation

Conducting a site survey

Power supply information

Survey the customer site to confirm that the location meets the requirements for installation of
the satellite modem. For complete site survey information, including site requirements, see the
Antenna Site Preparation and Mount Installation Guide (1035678-0001).
The key site survey tasks related to installation of the satellite modem are:
1. Make sure there is an unobstructed line of sight to the satellite specified on the Installation
Reference Sheet.
2. Review the Installation Reference Sheet for site-specific instructions.
See also
Connecting the power supply
The power supply is included in the satellite modem shipping carton.

Figure 3: AC power supply for the HN9200 satellite modem

Before proceeding, make sure you have the correct power supply. Check the part number on the
power supply and refer to
Figure 3: AC power supply for the HN9200 satellite modem
7.
• Always use the power supply provided with the satellite modem. The modem's performance
may suffer if the wrong power supply is used.
• Connect the AC/DC power supply to a three-wire, grounded outlet with an input of 110/240
VAC. A suitable surge protector is recommended to protect the satellite modem from possible
damage due to power surges.
• Always connect the DC power cord to the HN9200 rear panel before applying power to the
power supply. If you apply power to the power supply and then connect the DC power cord,
the satellite modem may not perform properly and could be damaged.
• Observe the power standards and requirements of the country where it is installed.
on page 17.