DD+DIS148.05E
►
Purpose of this document
This document contains all planning data including the required measures to be carried
out on site prior to the machine delivery.
This chapter is divided into:
•
construction planning data
•
technical connection and performance data
•
safety instructions, listing of certificates
►
Document History
Edition.
Revision
1.2
►
Referenced Documents
Document
n.a.
The controlled version of this document resides on MedNet. Any printed copy of this document is uncontrolled.
Edition 1, Revision 2
12-2007
Release
Changes
Date
compared to previous Version 1.1:
•
11-2007
Adapted scope of delivery (Before: Only English user
manual delivered as paper manual; Now: additional
Chinese simplified and Spanish). See section 3.1
•
Added detailed specifications for power cables which
are part of delivery. See section 3.1
•
Corrected wrong outlet and cable specification for US:
Wrong: NEMA 6-15p outlet/cable
Correct: NEMA 5-15p outlet/cable.
See section 8.
Title
n.a.
DOCUMENT CONTROL NOTE:
DRYSTAR 5302
5366/100
Installation Planning
Chapter 11 / 3
Agfa Company Confidential
1
2
3