Page 76 of 436
Positioning and leveling equipment
NN43021-310
Standard 06.01
c.
Position a level across the top module cover on the front of the
column.
d.
Loosen the locking nuts on the feet.
e.
Adjust the feet on each pedestal up or down to level the column.
f.
Perform step a to step e for leveling the rear of the system.
g.
Tighten the locking nuts.
Note: Leave at least 12.5 mm (1/2 in.) between the floor and the bottom
of the pedestal for air flow required by the blower unit.
3
For a multiple-column system, install NT8D49 Spacer Kits between
columns.
a.
Remove the front and rear module covers.
b.
Remove the front and rear intake grills, if not already removed.
c.
Remove the trim plates from the module side where the spacer will
be attached by removing the four screws securing the trim plates to
the module.
d.
Remove the side panel from the module's side where the spacer is
being attached by removing the four screws securing the side panel
to the module.
e.
Attach gaskets to both sides in the front section of each spacer (see
Figure 23).
March 2013