Reviewing Core/Net module placement
NN43021-310
Standard 06.01
Cabling Common Equipment in a Single Group system
Core/Net modules can be installed side-by-side on top of separate pedestals
(see Figure 77) for power and cooling redundancy or in a stacked
configuration (see Figure 78) in a single column.
Core/Net 1 is always on the left. Core/Net 0 is always on the right.
Figure 77
Stacked configuration of Core/Net modules
March 2013
553-AAA0757