Powering up the system and initial loading
STAT XSM
****
6
Clear the display and minor alarms on both Cores:
LD 135
CDSP
CMAJ
CMIN ALL
7
Test the clocks:
a.
Verify that the clock controller is assigned to the active Core:
LD 60
SSCK x
SWCK
****
8
Verify that the Clock Controllers are switching correctly:
SWCK
SWCK
9
Check applications.
10 Check dial tone.
March 2013
Check the system monitors
Exit program
Load program
Clear displays on the cores
Clear major alarms
Clear minor alarms
Load program
Get status of the clock controllers (x is "0" or "1"
for Clock 0 or Clock 1)
Switch the Clock (if necessary)
Exit program
Switch Clock
(Wait 30 seconds)
Switch Clock again
End of Procedure