96
7.1. Linear Axis
Caution
For every maintenance operation, please verify the axial backlash in the ball screw. If it is greater than 0.2 mm, the linear
axis must be replaced.
7.1.1. Components lubrication
Info
If needed, clean the components before the lubrication.
Info
Recommended lubricant : LUB-KC1.
Ball Screw and Bearing Guide Lubrication
Lubrication of the axis should be done every 2 years considering a typical use of 80h/week. When lubricating, move the carriage all
over the axis stroke to distribute the lubricant uniformly.
Cover Strip and Guide Rail Lubrication
Lubrication have to be done if it is needed or when the component doesn't have its grease film anymore.
Need help?
Do you have a question about the PALLETIZING SOLUTION AX Series and is the answer not in the manual?