Port Name
(6) RST
(7) SD
(8) SW1–4
Procedure
Step 1 Check the alarm indicator. If an alarm is displayed, clear the alarm.
Step 2 Verify the MDU configurations based on the integrated UPS user manual.
During the MDU power-on commissioning, you are not allowed to modify the MDU initial
configurations unless you are authorized by onsite Huawei engineers.
Step 3 Enter a user name and password to access the MDU, set the user name, password, time, and
language, and check that the initial parameter settings are correct.
----End

8.2 Commissioning smart cooling products

Prerequisites
The power-on commissioning for the upstream PDC of air cooled precision smart cooling
products is completed.
Issue 02 (2019-12-20)
Port Description
app on the mobile phone to
obtain the initial startup
password.
Insert the USB flash drive,
import and export the
configuration file, export run
logs, and upgrade software.
Reset the MDU.
SD card slot
DIP switch
The ports are protected by a security mechanism.
For the setting method, see the integrated UPS user manual.
Copyright © Huawei Technologies Co., Ltd.
8 Commissioning Core Components
Remarks
N/A
N/A
N/A