FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
----End
Follow-up Procedure
Table 8-19
Table 8-19 Follow-up procedure
If You Want To...
Query the information about a camera
Refresh the camera list
8.5 Commissioning Fire Extinguishing Devices
8.5.1 Commissioning Fire Extinguishing Devices (Standard)
8.5.1.1 Commissioning the Fire Alarm Control Panel (standard)
Prerequisites
Initial configuration parameters have been set for the fire alarm control panel before delivery
and do not need to be set onsite.
Preparations
Tools: none
Documents required: power supply and distribution system diagram, documents delivered
with the agent releasing control panel, fire extinguishing system conceptual diagram
(standard), fire extinguishing device layout diagram (standard)
Skill requirement: fire engineer
Procedure
Step 1 Switch on the input power circuit breaker of the fire alarm control panel for the protected area
by referring to the power supply and distribution system diagram.
Step 2 Switch on the active and standby power supply to power on the fire alarm control panel.
Issue 02 (2019-12-20)
describes the operations that can be performed on the Discovery Camera page.
For the diagrams, see the initial configuration parameter manual for the solution in use.
Copyright © Huawei Technologies Co., Ltd.
8 Commissioning Core Components
Then...
1. On the Discovery Camera page, specify
one or multiple of the keywords Code,
Name, and IP Address.
2. Click Search.
To reset the search criteria, click Reset.
On the Discovery Camera page, click
Refresh. The camera information in the list
is refreshed.
108