Optional) Commissioning The Ibox And Ibat; Setting Ibox And Ibat Parameters - Huawei FusionModule1000A Commissioning Manual

Prefabricated all-in-one data center
Hide thumbs Also See for FusionModule1000A:
Table of Contents

Advertisement

FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
----End

8.3.2 (Optional) Commissioning the iBOX and iBAT

If the iBOX and iBAT are configured, perform the following steps to commission them.

8.3.2.1 Setting iBOX and iBAT Parameters

Procedure
Step 1 Log in to the ECC800 WebUI as an administrator.
Step 2 Choose Monitoring > Power Distribution > iBOX/CIM > Running Parameters.
Step 3 Click Unhide All Advanced Signals, set iBOX single battery qty., Batt. installation time,
Single battery capacity, Current source, and Battery string No.. Retain default values for
other parameters.
Table 8-10 Setting iBOX parameters
Parameter
iBOX/CIM single
battery qty.
Batt installation
time
Single battery
capacity
Current source
Battery string No.
----End
Issue 02 (2019-12-20)
After the first login, change the password in time to ensure account security and prevent
unauthorized network attacks, such as data tampering. Huawei will not be liable for any security
issues caused by your failure to change the default password in time or password loss after changing.
Change the password of the user account periodically.
Record and keep the password properly. If you forgot the password, you will be unable to log in to
the WebUI.
When Event Notification is configured, password retrieval is supported.
An account is logged out due to timeout if no operation is performed within 10 minutes after system
login.
A maximum of three users can log in to the ECC800 WebUI at the same time.
Description
Total number of batteries monitored by
the iBOX/CIM
Actual time at which batteries are
installed
Single battery capacity refers to the
capacity of a single battery in a battery
string managed by the iBOX.
0–xxxA Hall
The actual specifications of the Hall
effect sensor prevail.
Set this parameter based on the planned
codes for iBOXs and battery strings.
Copyright © Huawei Technologies Co., Ltd.
8 Commissioning Core Components
Remarks
Set this parameter based
on the battery parameter
planned by the customer.
-
Obtain the battery capacity
from the battery label or
document.
-
Set this parameter based
on the customer's plan.