Procedure
Step 1 Turn off the upstream switch of the emergency light power cable.
Figure 8-36 Emergency light
Step 2 Remove the protective cover of the emergency light.
Step 3 Remove the red pin of the emergency light. The emergency light turns on.
Figure 8-37 Removing the red pin
Step 4 Reinstall the protective cover of the emergency light.
Step 5 Turn on the upstream switch of the emergency light power cable.
Step 6 Press the red button of the emergency light. The emergency light turns on. When you release
the red button, the emergency light turns off.
Issue 02 (2019-12-20)
For the diagrams, see the initial configuration parameter manual for the solution in use.
The emergency light turns off, and the power indicator turns on.