FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
Documents: fire extinguishing system conceptual diagram (standard), fire extinguishing
device layout diagram (standard)
Skill requirement: fire engineer
Procedure
Step 1 Disconnect cables from the electromagnetic valve.
Figure 7-1 Disconnecting cables from the electromagnetic valve
Step 2 Switch on the active and standby power supplies to the fire alarm control panel.
Step 3 Check whether the fire alarm control panel displays any alarm. If an alarm is displayed, clear
the alarm before performing follow-up operations.
Step 4 Press KEY ON/OFF, QUERY TIME, and MANUAl/AUTO in turn to set the fire alarm
control panel to the automatic mode.
Issue 02 (2019-12-20)
For the diagrams, see the initial configuration parameter manual for the solution in use.
Copyright © Huawei Technologies Co., Ltd.
7 System Commissioning
37

Advertisement

Table of Contents
loading

This manual is also suitable for:

V200r003c10

Table of Contents