8.5.1.2 Commissioning the Emergency Lights (standard)

Prerequisites
The sockets of the emergency light have been powered on.
Preparations
Tools: step ladder, needle-shaped tool
Documents required: power supply and distribution system diagrams, fire extinguishing
device layout diagram (standard)
Skill requirement: fire engineer
Procedure
Step 1 When you press down the TEST button on the emergency light, the emergency light turns on.
When you release the TEST button, the emergency light turns off.
Step 2 When you unplug the power plug of the emergency light, the emergency light turns on. When
you stab the small hole shown in the figure with a needle-shaped tool, the emergency light
turns off.
Figure 8-35 Small hole in the emergency light
----End
Issue 02 (2019-12-20)
For the diagrams, see the initial configuration parameter manual for the solution in use.
You can also turn off the emergency light by pressing and holding the TEST button for more than
5s.
If the result expected for each step appears, the emergency light is working properly.