Commissioning

2.1

Procedure when commissioning

The following steps are required when commissioning a drive:
Table 2- 1
Note
If motors with integrated DRIVE-CLiQ interface are used, when the Sensor Module is
replaced at the motor, all motor and encoder data should be saved in a non-volatile manner
by setting parameter p4692 = 1.
A hazardous voltage will be present in all components for a further five minutes after the
system has been shutdown.
Note the information on the component!
A project with Safety Integrated can be generated offline; an acceptance test must be
carried out when commissioning, which is only possible online.
Note
The design guidelines and safety information in the Equipment Manuals must be carefully
observed (refer to the documentation SINAMICS S120, Equipment Manual GH1 and GH2).
Commissioning Manual
Commissioning Manual, (IH1), 01/2012, 6SL3097-4AF00-0BP2
Commissioning
Step
Activity
1
Create project with STARTER.
2
Configure the drive unit in STARTER.
3
Save the project in STARTER.
4
Establish online operation with the target device in STARTER
5
Load project to target device.
6
The result: the motor rotates