Commissioning
2.4 Creating a project in STARTER
PROFINET
To create a project offline, you need the PROFINET address, the device type and the device
version, e.g. firmware version 4.5 or higher.
What to do?
1
Create a new project
90
How to do it?
1. Call the menu "Project > New ...".
The following default settings are displayed:
User projects: Projects already in the target
directory
Name: Project_1 (can be freely selected)
Type: Project
Storage location (path): Default (can be set as
required)
2. If necessary, correct "Name" and "Storage
location".
The project is created offline and
loaded to the target system when
configuration is complete.
Commissioning Manual, (IH1), 01/2012, 6SL3097-4AF00-0BP2