Check lists to commission SINAMICS S

Checklist (1) for commissioning booksize power units
The following checklist must be carefully observed. Read the safety instructions in the
Manuals before starting any work.
Table 1- 1
Are the environmental conditions in the permissible range?
Is the component firmly attached to the fixing points provided?
Is the specified air flow for cooling the devices ensured?
Have the ventilation clearances for the components been observed?
Is the memory card correctly inserted in the Control Unit?
Are all of the necessary components of the configured drive line-up available, installed
and connected?
Do the temperature monitoring circuits fulfill the specifications of protective
separation?
Have the DRIVE-CLiQ topology rules been observed?
Have the line-side and motor-side power cables been dimensioned and routed in
accordance with the environmental and routing conditions?
Have the maximum permissible cable lengths between the frequency converter and
the motor (depending on the type of cables used) been observed?
Have the power cables been properly connected to the component terminals with the
specified torque?
Have all of the remaining screws been tightened to the specified torque?
Has all wiring work been successfully completed?
Are all connectors correctly plugged in and screwed in place?
Have all the covers for the DC link been closed and latched into place?
Have the screens been correctly connected through a large surface area?
Commissioning Manual
Commissioning Manual, (IH1), 01/2012, 6SL3097-4AF00-0BP2
Checklist for commissioning (booksize)
1.2 Check lists to commission SINAMICS S
Check
Preparation for commissioning
OK
17

Advertisement

Table of Contents
loading

Table of Contents