First Commissioning, Vector Control Mode In The Chassis Format - Siemens SINAMICS S120 Commissioning Manual

Hide thumbs Also See for SINAMICS S120:
Table of Contents

Advertisement

Commissioning

2.7 First commissioning, vector control mode in the chassis format

STARTER diagnostic options
Under Component -> Diagnostics -> Control/status words
● Control/status words
● Status parameters
● Missing enable signals
2.7
First commissioning, vector control mode in the chassis format
An example provided in this chapter explains all the configuration and parameter settings, as
well as tests that are required for initial commissioning. Commissioning is carried out using
the STARTER commissioning tool.
Preconditions for commissioning
1. The commissioning preconditions (Page 15) have been met.
2. The commissioning checklists (Page 17) (Tables 1-1 and 1-2) have been completed and
3. The STARTER commissioning tool is installed and activated.
4. The drive system has been wired according to the specifications.
5. The communication between the PG/PC and drive system has been prepared.
6. The power supply of the Control Unit (24 V DC) has been switched on.
116
the points fulfilled.
– see the "Readme" file on the STARTER installation DVD
Commissioning Manual, (IH1), 01/2012, 6SL3097-4AF00-0BP2
Commissioning Manual

Advertisement

Table of Contents
loading

Table of Contents