CONCRETE PAD MOUNT
Install the operator, by taking the following steps:
1. Place the operator on the pad to best suit the
conduit as shown in Figure 2. Use the operator
as a template and center it on the pad. The
chain path must be parallel with the gate.
2. Assess any limitations in the chain path such
as gate support posts. Adjust the operator's
location as required. Mark the mounting
locations based on gate, operator, and chain
requirements. Mark the drill point at the center
of the slot to allow for adjustments. See Figure
3 and Figure 10.
3. Remove the operator from the concrete pad
and drill the holes for the concrete anchors.
See Tip.
4. Mount the operator with four ½ - 13 x 3½-inch
concrete anchors as shown in Figure 9.
5. For additional types of mounting options, refer
to the Appendix.
Chain to Gate
Ideal distance = 3¾" (9.5cm)
Min. distance = 2½" (6.4cm)
6.4"
(16.3cm)
.
10
5"
(26.7cm)
1.6"
(4.1cm)
Concrete
pad
Chain,
#40 Roller
Conduit
Cut Out
Mark the center of
10.4"
slo�ed holes (4x) for
(26.4cm)
concrete anchors:
½ - 13 x 3½"
19" minimum
(48.3cm)
Figure 11. Concrete Pad Dimensions and Overhead Gate View
Concrete
pad
Grade
level
TIP: To keep pinpoint accuracy while drilling the
mounting holes in the concrete, use a 3/16-inch
bit to pilot the holes and then move to a ½-inch
drill bit.
Gate
Gate Suppot
Posts
SlideSmart
Operator
21"
(53.3cm)
Direc�on of gate
movement when
opening
INSTALLATION
Figure 10. Concrete Anchors
Le� hand gate
(shown in full CLOSE
posi�on)
Chain resides inside
gate support posts
parallel with the gate.
SECURE
MX4505 Rev.H ©2022
½ - 13 x 3½"
concrete
anchors (x4)
Concrete
base
Gate
Suppot
Posts
PUBLIC