Commissioning

5.3 Check lists to commission SINAMICS S

5.3
Check lists to commission SINAMICS S
Checklist for commissioning booksize power units
Carefully observe the content of the following checklist, and read the safety instructions in
the manuals before starting any work.
Table 5- 1
Check
Are the environmental conditions in the permissible range?
Is the component firmly attached to the fixing points provided?
Is the specified air flow for cooling the devices ensured?
Have the ventilation clearances for the components been observed?
Is the memory card correctly inserted in the Control Unit?
Are all necessary components of the configured drive line-up available, installed and
connected?
Do the temperature monitoring circuits fulfill the specifications of protective separa-
tion?
Have the DRIVE-CLiQ topology rules been observed?
Have the line-side and motor-side power cables been dimensioned and routed in
accordance with the environmental and routing conditions?
Have the maximum permitted cable lengths between the frequency converter and the
motor (depending on the type of cables used) been observed?
Have the power cables been properly connected to the component terminals with the
specified torque?
Have all of the remaining screws been tightened to the specified torque?
Has all wiring work been successfully completed?
Are all connectors correctly plugged in and screwed in place?
Have all the covers for the DC link been closed and latched into place?
Have the shield supports been correctly connected through a large surface area?
Checklist for commissioning chassis power units
Carefully observe the content of the following checklist, and read the safety instructions in
the manuals before starting any work.
Table 5- 2
Activity
Are the environmental conditions in the permissible range?
Are the components correctly installed in the cabinets?
Is the specified air flow for cooling the devices ensured?
Is an air short-circuit between the air inlet and outlet for the chassis components pre-
vented by the installation arrangements?
Have the ventilation clearances for the components been observed?
66
Checklist for commissioning (booksize)
Checklist for commissioning (chassis)
Getting Started, 12/2018, 6SL3097-5AG30-0BP0
OK
OK