Alvarion BreezeMAX 3500 System Manual page 83

Hide thumbs Also See for BreezeMAX 3500:
Table of Contents

Advertisement

SU-IDU Installation
To install the SU-IDU:
1. It is assumed that the IDU-ODU cable is already connected to the
ODU (refer to to
Assemble an RJ-45 connector with a protective cover on the indoor
end of the IDU-ODU cable. Refer to
preparing the cable.
2. Connect the IDU-ODU cable to the RADIO connector. The RADIO
connector in the CPE-IDU-1D is located on the front panel as shown
in Figure 2-12.
3. Connect the power cord to the unit's AC socket, located on the rear
panel. Connect the other end of the power cord to the AC mains
after verifying that the unit is rated for the voltage in the country of
use; the AC raing is indicated on the back side of the CPE-IDU-1D.
NOTE
Brown
Blue
Yellow/Green
4. Verify that the POWER LED located on the front panel is lit,
indicating that the unit is supplying power to the radio port.
5. Configure the basic parameters and align the antenna as described
in the applicable sections of
6. Connect the 10/100 Base-T ETHERNET connector(s) to the data
equipment. The cable connection should be a crossed Ethernet if
connecting to a hub/switch and a straight cable if connecting
directly to a PC Network Interface Card (NIC).
NOTE
The length of the Ethernet cable connecting CPE-IDU-1D to the user's equipment,
together with the length of the IDU-ODU cable, should not exceed 100 meters.
7. Verify proper operation as described in the applicable section of
Chapter 3 –
Manual Revision 1.0
Connecting the SU's IDU-ODU Cable
The color codes of the power cable are as follows:
Phase
~
Neutral
0
Ground
Chapter 3 –
Commissioning.
Installing the CPE-IDU-1D Indoor Unit
on page 2-12).
Appendix A
for instructions on
Commissioning.