- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - Phase Descriptions
Test Numbers:
199 and 200
Function:
These tests verify the erase/write disable operation.
Procedure:
Disable write and erase operation on the EEPROM, then try to erase
Register 33, try to write Register 21.
Hardware Tested:
The EEPROM is tested.
Data Returned:
Supplemental Data: The value read from the register is returned.
Raw Data: The value expected to be read from the register is returned.
Test Numbers:
201 through 264
Function:
These tests verify that the contents of the EEPROM have been restored to
original values.
Procedure:
Write original contents to EEPROM; read
it
back and compare.
Hardware Tested:
The EEPROM is tested.
Data Returned:
Supplemental Data: The value read from the register is returned.
Raw Data: The value expected to be read from the register is returned.
GENERAL PURPOSE SYNCHRONOUS CONTROLLER
16-45

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 3B2 and is the answer not in the manual?

Table of Contents