Running the GTH IBERT Demonstration
The GTH IBERT demonstration operates one GTH Quad at a time. This section describes
how to test GTH Quad 115, while the remaining GTH Quads are tested following similar
steps.
Connecting the GTH Transceivers and Reference Clocks
Figure 1-1
board.
Note:
X-Ref Target - Figure 1-1
8
Send Feedback
shows the locations for all the GTH transceiver Quads on the Rev. B VC7222
Figure 1-1
is for reference only and might not reflect the current revision of the board.
Figure 1-1: GTH Quad Location