Energy chain X-module
1. Push the slide of the X-module up to the end stop so that the maximum possible length of the en
ergy chain lies flat.
2. Place cables and hoses from the energy chain Y into the energy chain X.
Between the energy chains
Tie together cables using cable binders.
Tie hoses separately from the cables.
Observe minimum bending radius of the cables and hoses.
Attach the cable bundle or hose bundle to the
cable base with cable ties.
7.3.7
Checking the energy chain
Perform movement of the energy chains over the respective entire stroke.
– The energy chain must be able to move without hindrance.