Checking Assembly And Connections; Configuring The Settings At The Interface; Test The Function Of The Automation System Cpx-Ap-I (Without Higher-Order Controller); Commissioning In Network (With Higher-Order Controller) - Festo CPX-AP-I Manual

Automation system
Hide thumbs Also See for CPX-AP-I:
Table of Contents

Advertisement

Diagnostics

8.1

Checking assembly and connections

1. Check that the modules are installed securely.
2. Check connection of functional earth FE.
3. Check that connected lines are seated firmly.
8.2

Configuring the settings at the interface

If necessary, configure the settings using the control elements on the interface.
Detailed information on the control elements of the applicable interface
è Product-specific documentation
8.3
Test the function of the automation system CPX-AP-I
(without higher-order controller)
1. Switch on PS and PL power supplies.
2. Test the response of the automation system CPX-AP-I:
– Connected actuators
– LED displays
The following LED displays must be green:
– [SD] system diagnostics (only available for interfaces)
– [MD] module diagnostics (available for all modules)
– [PL] voltage PL (only available for interfaces, electrical interfaces and modules with outputs)
8.4

Commissioning in network (with higher-order controller)

Information on commissioning on the network è Instruction manual for the applicable interface
9

Parameterisation

Various parameters are available to adapt the automation system CPX-AP and the modules to the
application and to access the corresponding data.
Detailed information on the parameters è Product-specific documentation
10
Diagnostics
10.1

Diagnostics options

Various options are available for error diagnostics, depending on the parameterisation and network
protocol used:
– LED displays on the product
– Internal System Diagnostics
– Diagnostics via the host system
24
Festo — CPX-AP-I — 2022-06a