Appendix A Commissioning; Start-Up Commissioning Services - Allen-Bradley PowerFlex 7000 User Manual

Medium voltage ac drive air-cooled (‘a’ frame) – forge control
Hide thumbs Also See for PowerFlex 7000:
Table of Contents

Advertisement

Start-up Commissioning
Services
7000 "A" Frame
Commissioning
Start-up will be performed at the customer's site. Rockwell
Automation requests a minimum of four- (4) weeks notice to
schedule each start-up.
The standard Rockwell Automation work hours are between 9:00
AM to 5:00 PM EST, (8 hr/day) Monday through Friday, not
including observed holidays. Additional working hours are available
on a time and material basis.
Rockwell Automation recommends the following:
Drive Commissioning
1.
A pre-installation meeting/conference call with the customer to
review:
The Rockwell Automation Start-up Plan
The Start-up Schedule
The Drive(s) installation requirements
2.
Inspect the drive's mechanical and electrical devices.
3.
Perform a tug test on all internal connections within the drive
and verify wiring.
4.
Verify critical mechanical connections for proper torque
requirements.
5.
Verify and adjust mechanical interlocks for permanent
location.
6.
Confirm all inter-sectional wiring is connected properly.
7.
Re-verify control wiring from any external control devices
such as PLCs, etc.
8.
Confirm cooling system is operational.
9.
Verification of proper phasing from isolation transformer to
drive.
10.
Confirm cabling of drive to motor, isolation transformer and
line feed.
11.
Collect test reports indicating megger / hipot test has been
performed on line and motor cables.
12.
Control power checks to verify all system inputs such as
starts/stops, faults, and other remote inputs.
A
Appendix
7000A-UM151E-EN-P - October 2018