Connecting a NetBackup 5330 compute node to
a primary shelf

Connecting a NetBackup 5330 compute node to a primary shelf

4
Slide the SFP completely into the port until it clicks into place.
Be sure that the metal handle on the end of the SFP is on the top. You do not
need to lift up the handle.
5
Verify that the SFP is seated properly.
The SFPs should be parallel to each other. They should not be twisted or
incompletely inserted.
The compute node ships with 4, 1 meter, Fibre Channel (FC) cables. FC cables
connect the compute node to the primary shelf canisters. To ensure communication
redundancy, connect the units exactly as described in this topic.
Note: If you have a 6TB primary shelf, you must upgrade to NetBackup Appliance
Release 2.7.1, or later. Refer to the NetBackup Appliance Upgrade Guide for
Release 2.7.x - RedHat Enterprise Linux (RHEL) Operating System, which is located
at the following site.
NetBackup Appliance documentation
The following diagrams and tables show the locations of the FC ports on both
components.
Hardware installation procedures