Connecting one expansion shelf to a primary shelf

Connect compute node slot 4, port 1 to primary shelf canister A, FC Ch2.
3
Verify that the connections match the ports in the following diagram.
Compute node
Primary Storage Shelf
A
B
See
"Connecting one expansion shelf to a primary shelf"
This topic describes the process of adding one new expansion shelf to an existing
primary shelf and compute node.
You can also use these instructions to install and connect an expansion shelf at
the same time you install a primary shelf and a compute node.
Note: If you have a 6TB expansion shelf with a 6TB or 3TB primary shelf, you must
upgrade to NetBackup Appliance Release 2.7.1, or later. Refer to the NetBackup
Appliance Upgrade Guide for Release 2.7.x - RedHat Enterprise Linux (RHEL)
Operating System, which is located at the following site.
documentation
When you install a compute node and storage shelves at the same time, leave the
power turned off until all of the cabling is complete. Use the provided sequence to
turn on the devices.
Hardware installation procedures
Connecting one expansion shelf to a primary shelf
on page 54.