VERITAS NetBackup 5330 Installation Manual page 55

Appliance hardware
Table of Contents

Advertisement

Caution: Be sure to install the SAS cables correctly before you turn on the expansion
shelf. If you need to disconnect and reconnect cables on an operational expansion
shelf, there is a risk that the primary shelf cannot recognize the new configuration.
Prerequisites for adding an expansion shelf
Be sure that you have 4U of rack space for each new shelf. One shelf must be
close to the primary shelf.
Refer to the following section to verify that cable lengths are adequate for your
rack installation.
See
"Determining SAS2 cable length"
Be sure that you have 220VAC power input for the storage shelf.
Verify that the compute node and the primary shelf are connected correctly.
Compute node
Primary Storage Shelf
A
B
Hardware installation procedures
Connecting one expansion shelf to a primary shelf
on page 32.
55