2.5.4.4 Connect the Controlling and Expansion Chassis
Installment of the PZ-BS10 blade and PZ-BS11 blade(s)
must be completed prior to installation of the provided (CAT
5) expansion cabling.
Figure 3-41 PZ-BS11 Blade Installed (Cover Closed)
1.
Ensure Controlling and Expansion chassis are powered
down.
2.
Using the NEC provided CAT5 straight-through cable(s),
attach one end to each Expansion Chassis CN2 connector
on the PZ-BS11 blade (see
Cabling on page
CN3 or CN4 connector on the PZ-BS10 of the Controlling
Chassis.
Figure 3-42 System Expansion
3-32. Attach the opposite end to the CN2,
http//vietpro.com.vn
3-31