2. Commissioning

2.11 Checklist for commissioning the CPX terminal

2-66
If the safety concept of your machine/system permits, com-
mission the CPX terminal at first with both operating voltages
– but without compressed air. You can then test the CPX ter-
minal without triggering undesired reactions.
Note
Observe the general commissioning instructions
in the CPX system description and in the manual of your
controller.
Caution
The CPX terminal with bus node for PROFINET will also
start with incomplete configuration.
Check the configuration and address assignment of the
I/Os on the CPX terminal. For this purpose, you can force
the I/Os, if necessary (see CPX system description
P.BE-CPX-SYS-...).
An incomplete configuration will normally be displayed
with the diagnostics LED of the controller and in the on-
line diagnostics of your configuration software.
Approach:
Check the DIL switch settings and the network configura-
tion before using and replacing CPX terminals.
Ensure that the desired start parameterisation of the CPX
terminal will be recreated after a network interruption.
Make sure that, after replacement of individual modules
or of the entire CPX terminal, the new terminal is also
operated with the required parameter settings. (See also
section 2.8.1 for the start parameterisation and the note
on parameterisation using CPX-MMI or CPX-FMT in
section 2.8.4.)
Festo P.BE-CPX-PNIO-EN en 1407c English

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cpx-fb35Cpx-m-fb33Cpx-m-fb34Cpx-m-fb35Cpx-fb34

Table of Contents