118 Installation checklist
Check that ...
There is an adequately sized protective earth (ground) conductor between the motor
and the drive.
All protective earth (ground) conductors have been connected to the appropriate
terminals and the terminals have been tightened (pull conductors to check).
The supply voltage matches the nominal input voltage of the drive. Check the type
designation label.
The input power cable has been connected to appropriate terminals, the phase order
is right, and the terminals have been tightened. (Pull conductors to check.)
Appropriate supply fuses and disconnector have been installed.
The motor cable has been connected to appropriate terminals, the phase order is right,
and the terminals have been tightened. (Pull conductors to check.)
The brake resistor cable (if present) has been connected to appropriate terminals, and
the terminals have been tightened. (Pull conductors to check.)
The motor cable (and brake resistor cable, if present) has been routed away from other
cables.
The control cables (if any) have been connected to the control board.
If a drive bypass connection will be used: The direct-on-line contactor of the motor and
the drive output contactor are either mechanically or electrically interlocked (cannot be
closed simultaneously).
There are no tools, foreign objects or dust from drilling inside the drive.
Drive and motor connection box covers are in place.
The motor and the driven equipment are ready for start-up.