Tank-To-Pump Valve Installation - Idex Akron Bras SAM BOOST Operation Installation Maintenance Manual

For sam boost with smart nozzle n2p and uv780 display
Table of Contents

Advertisement

SAM BOOST™ WITH SMART NOZZLE N
It is recommended to install pressure transducer connectors oriented between 45° to
90° from horizontal to allow drainage and avoid sediment build-up.
5.5

TANK-TO-PUMP VALVE INSTALLATION

The SAM Boost™ System includes either a 3" or 4" Electric Boost™ Valve programmed for use with system.
Follow the steps below for valve installation:
Locate the original equipment valve,
Remove control elements at the valve & control panel,
Disconnect any drain lines as necessary.
Remove original valve.
Install the Electric Boost™ Valve in the original valve location with the mechanical override accessible
for use in emergencies.
Torque requirements for reattaching the valve adapters are 34 – 38 FT-LBS for 3" Boost™
o
valves, 60 – 70 FT-LBS for 4" Boost™ valves.
o
If clocking the valve is required, follow instruction on AKRON BRASS manual 127903
Sheet: FSG-MNL-00234
INSTALLATION, OPERATING, & MAINTENANCE MANUAL
PHONE: (800) 288.1161
www.akronbrass.com
Revision 2023-08-28
P AND UV780 DISPLAY
2
Page: 24 of 66

Advertisement

Table of Contents
loading

Table of Contents