Eaton Power Xpert 9395P-1100/1100 Installation And Operation Manual page 93

Table of Contents

Advertisement

Lors de l'évaluation du système de batterie, ne pas dépasser les capacités internes du chargeur de batteries.
Se reporter au chapitre
Chapter 10 Product Specifications
tensions maximales du chargeur de batteries.Ne pas installer une armoire endommagée. Signaler les
dommages au transporteur et communiquer avec un représentant du service Eaton immédiatement.
To install wiring to connections:
NOTE
An installed FI-UPM is always designated as UPM 4.
NOTE
Battery Cable Routing Requirements using Conduit:
* Each conduit must have a Positive, Negative, and Ground conductor
* There must be an equal number of positive and negative conductors in a single
conduit. Only one ground conductor is required in each conduit.
Battery Cable Routing Requirements using Raceway:
* Positive and negative battery cables must be run side by side in the raceway in an
alternating pattern (+ - + - + - + -).
* There must be a ground cable running in the raceway with the battery cables.
1.
Route the battery cables between the ISBM section and the battery system or battery disconnect. See
Figure
32,
Figure
33,
Figure
2.
If wiring the UPS for a common battery, proceed to Step 3; if wiring for a separate battery, proceed to Step
5.
3.
Using hardware from the external wiring terminal hardware kit (see
negative, and ground DC power wiring from the battery systems or disconnects to the ISBM section
battery and ground terminals. Use one set of terminals for each UPM as shown in
paragraph for wiring and termination requirements.
4.
Proceed to Step 6.
5.
Using hardware from the external wiring terminal hardware kit (see
negative, and ground DC power wiring from the battery systems or disconnects to the ISBM section
battery and ground terminals. Use one set of terminals for each UPM. See paragraph
3.2.4 UPS System Power Wiring Preparation
6.
After wiring the UPS system to the facility power and critical load, be sure to ground the system according
to local and/or national electrical wiring codes.
7.
If wiring interface connections, proceed to paragraph
otherwise, proceed to Step 8.
8.
When all wiring is complete, reinstall the top and bottom safety shield panels removed in paragraph
4.8.1 External Power Wiring
9.
Reinstall the left front panel removed in paragraph
secure with the retained hardware.
ATTENTION!
35, and
Figure 36
for wiring access information and terminal locations.
for wiring and termination requirements.
Installation, Step 2. Secure with the retained hardware.
4.8.1 External Power Wiring
Eaton
®
Power Xpert
®
9395P-1200 Installation and Operation Manual 164000500—Rev 11
sur les notices techniques pour connaître les
Table
17), connect the positive,
Table
17), connect the positive,
3.2.5 UPS System Interface Wiring
Installation, Step 1 and
UPS System Installation
Figure
36. See
Preparation;
75