15. In the ISBM section (see A in
connectors attached. Remove the wire ties securing the harnesses and carefully remove the harnesses
from the protective cage. If necessary, loosen the screws securing the protective cage.
16. Locate the mating P50 connector in the UPM section wireway (see B in
connector to the J50 connector.
17. Locate the mating P51 connector in the UPM section wireway (see B in
connector to the J51 connector.
18. Locate the mating P61 connector in the UPM section wireway (see B in
connector to the J61 connector.
19. Locate the mating P70 connector in the UPM section wireway (see B in
connector to the J70 connector.
NOTE
One intercabinet interface cable is supplied coiled against the left side panel of the UPM
section (see B in
20. In the UPM section (see B in
the cable to the interior left side panel of the UPM section. Route this cable through the round wiring
access in the right side panel of the ISBM section (see B in
21. In the ISBM section, locate the J39 inverter CAN connector on the Pl1 interface board and connect the RJ-
45 CAN cable connector to the J39 connector (see
22. Dress the interface harnesses and secure in place with wire ties as necessary to prevent wire damage.
23. When all wiring is complete, reinstall the safety shield panels removed in previous steps.
24. Reinstall the front wireway panel.
25. If installing a four UPM UPS, proceed to paragraph
to Step 26.
26. If installing a battery system, proceed to paragraph
Step 27.
27. If installing a tie cabinet or distribution panel for a distributed bypass system, proceed to paragraph
4.7 Distributed Bypass Tie Cabinet
4.8 Installing UPS External and Battery Power Wiring
Figure
30), locate the coiled wiring harnesses with the J50, J51, J61, and J70
Figure
28).
Figure
28), locate the coiled RJ-45 CAN cable. Remove the wire ties securing
Figure 29
4.5 Field Installed UPM
Installation; otherwise, proceed to paragraph
Eaton
®
Power Xpert
®
9395P-1200 Installation and Operation Manual 164000500—Rev 11
Figure
Figure
Figure
Figure
Figure
28).
and
Figure
30).
Installation; otherwise, proceed
4.6 Battery System
Installation; otherwise, proceed to
UPS System Installation
28) and connect the P50
28) and connect the P51
28) and connect the P61
28) and connect the P70
61