UPS System Installation
I I n n s s t t a a l l l l a a t t i i o o n n C C h h e e c c k k l l i i s s t t
o All packing materials and restraints have been removed from each cabinet.
o Each cabinet in the UPS system is placed in its installed location.
o A cabinet grounding/mounting kit is installed between any cabinets that are bolted together.
o All conduits and cables are properly routed to the UPS and any ancillary cabinets.
o All power cables are properly sized and terminated.
o Battery cables are terminated on E4 (+) and E5 (–).
o Battery aux contact signal wiring is connected from the UPS to the battery disconnect.
o Battery shunt trip signal wiring is connected from the UPS to the battery disconnect. (OPTIONAL).
o LAN and telephone drops are installed.
o All telephone and LAN connections have been completed.
o A ground conductor is properly installed.
o Air conditioning equipment is installed and operating correctly.
o The area around the installed UPS system is clean and dust–free. (It is recommended that the UPS be
installed on a level floor suitable for computer or electronic equipment.)
o Adequate workspace exists around the UPS and other cabinets.
o Adequate lighting is provided around all UPS equipment.
o A 120 Vac service outlet is located within 7.5 meters (25 feet) of the UPS equipment.
o The REPO device is mounted in its installed location and its wiring is terminated inside the UPS cabinet.
o The normally-closed (NC) Emergency Power-off contact (pins 1 and 2 on TB1) is jumpered if not used.
o Alarm relays and building alarms are wired appropriately. (OPTIONAL)
o A remote battery disconnect control is mounted in its installed location and its wiring is terminated inside
the UPS and battery cabinet. (OPTIONAL)
o Accessories are mounted in installed locations and wiring is terminated inside the UPS cabinet. (OPTIONAL)
o The debris shield covering the UPS cabinet ventilation grill is removed.
o Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.
92
Eaton
®
Power Xpert
®
9395P-1200 Installation and Operation Manual 164000500—Rev 11

Advertisement

Table of Contents
loading

Table of Contents